Unbenannt

<%PostCommentPage%> <%PhotoAlbumPage%> <%ProfilePage%>

PMI-200 Prüfungsvorbereitung Prüfungsfragen deutsch

{ 10:18, 24 December 2018 } { 0 comments } { Link }

PMI-200 Prüfungsvorbereitung Prüfungsfragen deutsch PMI-Agile Certified Practitioner (PMI-ACP) Exam www.it-pruefungen.ch
QUESTION 1
Retrospectives provide an opportunity for the team to:
A. Reflect at the end of every iteration and identify improvements that will increase the quality of the product.
B. Participate in a mandatory meeting to share status updates across the team and to ensure that everyone is on track.
C. Understand from the management if the project is achieving the Scope, Quality, Cost, and Schedule goals.
D. Set goals at the beginning of the iteration and identify requirements that can be delivered in that iteration.
Answer: A
QUESTION 2
When interacting with team members, the Agile project manager should:
A. Ask team members to do things by phrasing the statement as a request rather than as a demand.
B. Ignore team member input and emotions when important decisions have to be made.
C. Proceed cautiously when requesting team members to do something likely to make them unhappy.
D. Disagree with the team based on the merit of the issue without considering how the team is feeling.
Answer: A
IT-Prüfungen PMI-200 PMI-Agile Certified Practitioner (PMI-ACP) Exam https://www.it-pruefungen.de/PMI-200.htm
QUESTION 3
An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:
A. procurement processes by requiring vendors to ship materials as needed.
B. project cost management by making incremental payments on contracts.
C. customer satisfaction by specifying project shipping dates in the contract.
D. project Return on Investment (ROI) by releasing individual features to market.
Answer: D
QUESTION 4
Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can infer that:
A. Work was removed from the Product Backlog.
B. Work was added to the Product Backlog.
C. The team’s velocity increased.
D. The team’s velocity decreased.
Answer: B
PMI-200 Prüfungsfragen PMI-Agile Certified Practitioner (PMI-ACP) Exam www.it-pruefungen.ch
QUESTION 5
What is used to provide a simple medium for gathering basic information about stories, recording high-level requirements, developing work estimates, and defining acceptance tests?
A. Story card
B. Burn down chart
C. Retrospective
D. Storyboard
Answer: A


{ Kommentar schreiben }

{ Last Page } { Page 4 of 11 } { Next Page }

ber Mich

Start
Mein Profil
Archiv
Freunde
Mein Photo Album

«  July 2019  »
MonTueWedThuFriSatSun
1234567
891011121314
15161718192021
22232425262728
293031 

Links


Kategorien


Letzte Beitrge

Prüfungsvorbereitung zur AZ-101 Prüfungsfragen deutsch englisch
Microsoft Azure AZ-100 Prüfungsfragen Prüfungsvorbereitung
PMI-100 Prüfungsfragen, PMI-100 PDF Software
PMI-200 Prüfungsvorbereitung Prüfungsfragen deutsch
PMI-001 Prüfungsfragen Prüfungsvorbereitung

Freunde